Offshore main span of Xiamen-Jinmen Bridge (Xiamen section) completed, opening expected by the end of the year

According to Fujian Provincial State-owned Assets Supervision and Administration Commission on 13 November, the offshore main bridge of the Xiamen-Jinmen Bridge (Xiamen section) was closed at 1 a.m. on 10 November, after the final steel box girder of Lot A2 was positioned precisely. Work on the main structural body of the offshore bridge has finished, and the project has moved into final construction stages ahead of opening, laying foundations for the scheduled opening before the year end.

The closed steel box girder sits between piers 29 and 30 of the main bridge at Lot A2, weighing 3,318 tonnes. The lifting operation required strict precision control, with the reference temperature for closure kept steady at around 22 degrees Celsius. A 5,500-tonne floating crane carried out the hoisting, and ten synchronised positioning jacks adjusted the girder to achieve accurate alignment once it was moved into the closure gap.

97.png

The transport project supports cross-strait integrated development and faces tough construction constraints. The heaviest single steel box girder, including lifting fittings, reaches 4,500 tonnes. The construction sea area falls within protected zones for Indo-Pacific humpback dolphins and amphioxus, requiring stringent environmental standards. Monsoon and typhoon conditions affect the site for up to 183 days each year, alongside tight timelines and heavy marine traffic control demands. Construction teams monitored risks related to lifting, ecological protection and navigation throughout the process, managed quality and safety standards, and balanced construction progress with marine navigation and environmental safeguards to deliver the closure milestone.

The completed section is the non-navigable span east of the Liuwudian Waterway, the final closure segment of the offshore main bridge. The 14.2-kilometre offshore main bridge comprises twelve separate sections. Works on deck surfacing, electromechanical systems and traffic safety installations are now advancing. The full Xiamen-Jinmen Bridge (Xiamen section) stretches approximately 19.6 kilometres, with a main route of 17.34 kilometres. Its sea-crossing section features eight traffic lanes and a design speed of 100 kilometres per hour. Upon commissioning, the link will connect with Xiang’an International Airport and existing Xiamen-Jinmen shipping routes to form a combined land, sea and air transport network for cross-strait travel, providing key transport support for Fujian’s cross-strait integrated development demonstration zone.