China Datang launches heating supply across multiple regions for winter

According to China Datang Corporation Ltd, 18 November, heating supply has been fully activated by the group in Beijing, Liaoning, Jilin and other locations by 15 November, to meet residential heating demand.

A heat storage tank with a capacity of more than 30,000 cubic metres, built by Datang Gaojing Thermal Power Company, came into operation on 15 November in Beijing. Together with a recently commissioned zero-carbon waste heat project, it delivers new capacity to the capital’s heating network. 

7.png

The facility generates extra heat without burning additional fossil fuels as a zero-carbon heat source. 

After commissioning, the site’s heating capacity rises by 20.4 per cent. The scheme will cut gas consumption by 45 million cubic metres each year, add 1.59 million gigajoules of green heat and reduce carbon dioxide emissions by 85,000 tonnes, reinforcing heating security and supporting low-carbon transition in Beijing.

Datang Liaoning Branch started heating on 1 November, serving Shenyang, Jinzhou, Huludao and the Shenfu Demonstration Zone. Ahead of the heating season, the branch inspected systems for leaks and faults, completing 2,747 maintenance tasks and renewing 24.46 kilometres of ageing heating pipelines.

All heating subsidiaries of China Datang operate a 24-hour on-call roster once the heating season begins. Heating parameters are adjusted dynamically in response to temperature changes. Emergency repair teams and materials are kept ready, while heating service channels remain open to maintain stable heating for residents.