Main construction starts on Unit 4 of CGN’s San’ao nuclear power project in Zhejiang
According to China General Nuclear Power Group, the first concrete pour for the nuclear island of Unit 4 at the San’ao nuclear power project in Zhejiang got underway on 10 November, marking the formal start of the unit’s main works and the full roll-out of phase two of the scheme.
The site sits within Wenzhou, Zhejiang Province. Unit 4 forms part of the project’s second phase and is the third nuclear unit launched by the group this year. It adopts Hualong One, a third-generation nuclear power design with fully independent intellectual property rights. Once operational, the unit is projected to generate 9 billion kilowatt-hours of electricity each year, enough to cover the annual power needs of roughly one million people.
The pour covers approximately 8,820 cubic metres of concrete and is scheduled to run for 60 hours. The site team has refined workflows, upgraded intelligent tooling and rolled out incremental improvements while maintaining safety and quality standards, to keep construction milestones on track. Prefabricated removable retaining walls and hot-upsetting techniques for embedded components have already been deployed on site. Modular assembly and automated welding methods will be adopted in later stages, creating replicable construction practices for comparable nuclear builds.

Large-scale deployment of intelligent plant equipment stands out as a core technical feature. Automated production lines for reinforcing steel and embedded parts have been built to tackle quality control challenges associated with heavy-volume fabrication of nuclear island components. Robots for welding embedded fittings and rebar supports, alongside an automated platform for anchor block installation, replace conventional manual work. The welding robots lift first-pass welding acceptance rates to 90 per cent and boost welding output by roughly twofold and fourfold respectively. The anchor plate installation platform delivers a 100 per cent first-time acceptance rate and speeds up installation by around 11.5 times.
The San’ao complex is planned for six Hualong One reactors across three phases, with four units approved to date. Unit 1 has entered commercial operation, Unit 2 has completed its first fuel loading, and Unit 3 is undergoing main structural works for auxiliary buildings around its nuclear island. Construction proceeds in line with the agreed timetable. When all six units reach operation, the total annual output will exceed 54 billion kilowatt-hours, equivalent to nearly 80 per cent of Wenzhou’s current annual electricity consumption. The facility will cut annual coal use by more than 16.35 million tonnes and reduce carbon dioxide emissions by close to 50 million tonnes, supporting low-carbon transition across the Yangtze River Delta and stable power supply for computing hubs and smart industry activity.