All twelve tunnels finished on Section 4 of Shenzhen–Nanning high-speed railway

According to the Guangdong Provincial State-owned Assets Supervision and Administration Commission, the Niujiaojing Tunnel, part of Section 4 of the Shenzhen–Nanning high-speed railway, has broken through. 

The tunnel is managed by Guangdong Railway Construction Investment Group and constructed by Guangdong Construction Engineering Holding Group. 

Its breakthrough marks the completion of all twelve tunnels within this section, laying groundwork for subsequent beam erection, ballastless track laying and the scheduled opening of the full line.

Situated in Gaoyao District of Zhaoqing, Niujiaojing Tunnel is a single-bore double-track high-speed tunnel designed for a speed of 350 kilometres per hour. It crosses complex geological formations and passes beneath existing high-voltage transmission towers, ranking as a key and challenging control structure for the section.

56.png

The project team deployed ground-penetrating radar and advanced drilling for geological forecasting, adjusting excavation sequences and support parameters dynamically to address geological hazards. 

Mechanical excavation was adopted for zones adjacent to the high-voltage towers, with a digital monitoring system running continuously to track conditions and secure safe breakthrough.

The Shenzhen–Nanning high-speed railway forms a vital transport route linking the Guangdong-Hong Kong-Macao Greater Bay Area with Guangxi and wider south-western China. The finished line will extend the reach of the Greater Bay Area, improve passenger rail services between Guangdong and Guangxi, ease travel for residents along the route and support regional coordinated development.

The construction team will maintain strict safety and quality controls and carry out the remaining works to meet the opening timetable.